Construction Update

Seal and Stripe is 65% completed

Pool C and D construction will begin January, 2018 and will be completed in February 2018. Pool C is estimated to be completed on March 15 and Pool D is estimated to be completed on April 15.

Landscaping design is in progress and work will begin in February 2018.

Construction is always estimated based on priority and product availability. Dates can vary. We appreciate your patience! Come visit and see our updated Leasing Office or spend a day relaxing by the upgraded A and B pools!